April 4, 2005 |
|
Upgrade to Enterprise Version 4.72 |
|
January 9, 2004 |
|
First pay check under the SAP
system |
|
December 22, 2003 |
|
First SAP data input by campus
employees |
|
December 12-21, 2003 |
|
Cutover conversion from HRIS to SAP |
|
December 12, 2003 |
|
Last data entry into legacy HRIS system |
|
October 6-November 10, 2003 |
|
Payroll parallel simulations and testing |
|
July/August, 2003 |
|
User Acceptance Testing (UAT) |
|
June, 2003 |
|
System Integration Testing Completed |
|
May, 2003 |
|
Train-the-Trainer Initial
Training |
|
|
|
SAP Login and Navigation
Training |
|
April, 2003 |
|
HR Implementation Workshop |
|
|
|
Data Preparation |
|
2002/2003 |
|
System Configuration |
|
|
|
System "Design" |
|
|
|
Gap Analysis Workshops |
|
2001 |
|
Requirements Assessment |
|
|
|
Project Team Formation |
|
|
|
Requirements Definition |
|
|
|
Creation of SyTEC (State
System Technology Consortium) |
|
|
|
Contract Awarded to SAP and
Unisys |
|
2000 |
|
Request For Qualified
Contractors |
|
1999 |
|
Board of Governors Accepts
Gartner Recommendation |
| |
|
|
| |
|
|
|
Finance and Materials
Management (FI-MM) |
|
April 4, 2005 |
|
Upgrade to Enterprise Version 4.72 |
|
December 1, 2003 |
|
Go-live date |
|
November
24-30, 2003 |
|
Cutover conversion to SAP |
|
November 19, 2003 |
|
Cease input to legacy system |
|
September/October, 2003 |
|
Train-the-Trainer Sessions |
|
August 31, 2003 |
|
Submission of campus test data |
|
May - August, 2003 |
|
Data preparation and table building |
| |
|
|
| |
|
|
| |
|
|
| |
|
|
| |
|
|